Good afternoon Hoopeston Area Families,
The brick work is completed on the cafeteria addition. Electricians have lights installed inside the cafeteria. Painters are putting finishing touches on the walls. The window and door frames are installed with the glass scheduled to be on site October 11. The air handling units are scheduled to be shipped the week of October 2. Most of the work has been completed pending the air handling units being installed. The building of the sidewalk and parking lot immediately north of the band room and cafeteria addition is underway, once the materials are removed from inside the construction fence progress on the new pavement can begin to occur. We are working with the contractor to keep the athletic entrance open for events through the remainder of the construction. Enjoy the photos below of the ongoing construction
View Analytics